This page will be updated with the plan to 'SME 9.0 FINAL'.
 
This page will be updated with the plan to 'SME 9.0 FINAL'.
 
In addition to the roadmap there needs to be a short-term task list for community members. That will be linked from here.
 
In addition to the roadmap there needs to be a short-term task list for community members. That will be linked from here.
 +
 +
 +
===SME Server 9.1===
 +
The development of the SME Server 9.x series continues with the [http://wiki.contribs.org/SME9.1_Roadmap '''SME Server 9.1 Roadmap''']
    
= Pre-Alpha =
 
= Pre-Alpha =
Line 89: Line 93:       −
= SME 9.0 RC 1 =
+
= SME 9.0 RC 1 - Done 10th May =
 
* Maturity matches SME 8.0
 
* Maturity matches SME 8.0
 
* Extensive testing need to prove maturity
 
* Extensive testing need to prove maturity
    +
'''Status:''' Achieved, May 10th
   −
= SME 9.0 Final =
+
 
 +
= SME 9.0 Final - Done 28th June =
 
* Maturity matches SME 8.0
 
* Maturity matches SME 8.0
 
* Feature parity with SME 8.0, the intention is not to add new features
 
* Feature parity with SME 8.0, the intention is not to add new features
 
* Content identical to the final RC, just version and release note updates.
 
* Content identical to the final RC, just version and release note updates.
 
* The main contrib packages should be working at the final release.
 
* The main contrib packages should be working at the final release.
 +
 +
'''Status:''' Achieved, June 28th
 +
     